Slope Calculator — Rise, Percent, Degrees & Ratio

Convert between rise & run, percentage grade, degrees and ratio — the four ways slope appears on drawings, road signs, ramps and drainage plans. One tool, every format, with a live triangle you can actually read.

  • Rise & Run
  • Percent Grade
  • Degrees
  • Ratio (1:n)
  • Ramp Check
  • Drainage Check

Percent grade = (rise ÷ run) × 100. It is not the angle in degrees. 100% grade is a 45° slope, not a 100° slope.

Angle = arctan(rise ÷ run). A 1:12 ramp is about 4.76°, not 8.33°.

A smaller n means a steeper slope. 1:12 is steeper than 1:20.

Results are at rest

Set your inputs, then press Calculate Slope.

Inputs changed — press Calculate Slope to refresh.

Grade —
Angle —
Ratio —
Slope length: — Steepness: —
Flat 0%Moderate 10%Steep 25%Very steep 50%+
Rise Run θ

Slope Conversion Table

The four slope formats side by side — the quickest way to check a drawing against a road sign or a spec sheet.

Ratio (1:n)Grade (%)Angle (°)Typical use
1:2000.50%0.29°Land drainage, highway camber
1:1001.00%0.57°Drainage pipe minimum (large diameter)
1:801.25%0.72°Sewer lateral minimum (150 mm)
1:601.67%0.95°Drainage pipe minimum (100 mm)
1:502.00%1.15°Pavement crossfall, car park drainage
1:482.08%1.19°ADA cross slope maximum
1:402.50%1.43°Path drainage, patio fall
1:205.00%2.86°Gentle walkway, driveway approach
1:128.33%4.76°ADA/IBC ramp maximum
1:812.50%7.13°OSHA ramp maximum (cleats required)
1:616.67%9.46°Steep site access, temporary works
1:425.00%14.04°Very steep — check vehicle capability
1:250.00%26.57°Extreme — embankments only
1:1100.00%45.00°45° — not a ramp, a slope face

How to Calculate Slope

Slope is the relationship between how far something rises and how far it runs horizontally. The same slope can be written four ways. This is how each one is calculated.

Rise & Run

Measure the vertical difference (rise) and the horizontal distance (run) in the same unit.

Slope = Rise ÷ Run

Percent Grade

Multiply the slope ratio by 100. This is what road signs and drainage specs use.

Grade (%) = (Rise ÷ Run) × 100

Degrees

The angle of the slope from horizontal, using the inverse tangent.

Angle (°) = arctan(Rise ÷ Run)

Ratio (1:n)

Common on UK road signs and construction drawings. A smaller n means steeper.

n = 100 ÷ Grade (%)
Critical note — percent is not degrees

An 8.33% grade is a 4.76° angle. A 45° slope is 100% grade. Confusing the two is the most common mistake on site and in exams. The relationship is θ = arctan(% ÷ 100).

Slope Percentage and Ratio — Worked Examples

TaskGivenCalculationResult
Ramp design checkRise 0.6 m, Run 7.2 m0.6 ÷ 7.2 = 0.08338.33% — 1:12, meets ADA
Drainage pipeRun 30 m, fall 0.45 m0.45 ÷ 30 × 1001.5% — check pipe size minimum
Roof pitchRise 6 ft, Run 12 ft6 ÷ 12 = 0.550% — 6:12 pitch, 26.57°
Road gradientRise 4 m, Run 100 m4 ÷ 100 × 1004% — within motorway limit
Car park fallRise 0.1 m, Run 5 m0.1 ÷ 5 × 1002% — 1:50, standard crossfall
Path crossfallRise 0.02 m, Run 1 m0.02 ÷ 1 × 1002% — 1:50, ADA cross slope OK
Trench invertRun 45 m, fall 0.9 m0.9 ÷ 45 × 1002% — 1:50, good for 100 mm pipe
Stair angleRise 2.7 m, Run 3.6 marctan(2.7 ÷ 3.6)36.87° — steep stair, check code

Where Slope Calculations Are Used in Real Life

Slope is not an abstract geometry exercise. It governs access, safety, drainage and cost on every project.

Wheelchair ramps

ADA and IBC limit running slope to 1:12 (8.33%). Cross slope is capped at 1:48 (2.08%). Getting this wrong fails inspection.

Drainage and sewer pipes

Minimum gradients depend on pipe diameter — 100 mm pipe needs about 1:60 (1.67%), 150 mm about 1:80 (1.25%). Too flat and solids settle; too steep and water outruns solids.

Roof pitch

Roof pitch determines the roofing material, the rafter length, and whether the roof sheds water or snow. Low pitch (1:12 to 4:12) needs different membranes than steep pitch (8:12+).

Roads and highways

Motorways are capped at 3–4%, rural roads at 6–8%, and residential streets at 12%. Steeper than that and heavy vehicles lose traction, fuel consumption climbs, and drainage becomes critical.

Site grading and cut & fill

Grading plans specify slope as a percentage. A 2% fall across a car park is 1:50. Get the slope wrong and you either pond water or move more earth than you budgeted.

Stairs and stepped access

Stair angle is a slope. Comfortable stairs sit between 30° and 37°. Steeper than 42° and they become ladder-like; shallower than 26° and they feel like a ramp.

Excavation and trenching

Trench walls are battered back at a safe slope — typically 1:1 for stable soil, flatter for loose fill. OSHA and local codes set the allowed angles by soil type.

Bicycle and pedestrian paths

Shared paths are usually capped at 5% (1:20) for comfort and safety. Steeper gradients need handrails, landings or alternative accessible routes.

Slope Regulations and Standards

The key documents that set slope limits in construction. Check the project spec for which applies.

ADA Standards §405

US accessible design. Ramp running slope max 1:12 (8.33%), cross slope max 1:48 (2.08%).

IBC 1012.2

International Building Code ramp provisions. Max 1:12 running slope, 1:48 cross slope.

OSHA 29 CFR 1926.451

Construction ramps and walkways. Max 1:3 (20°) for walkways; steeper than 1:8 needs cleats.

OSHA 29 CFR 1910.25

General industry walking-working surfaces. Pedestrian ramps typically capped at 1:12.

AS 1428.1

Australian Standard for access and mobility. Ramp gradients and landings for public buildings.

BS 8300

UK accessible design. Ramp slope limits and landing requirements for buildings.

DIN 18040

German accessible construction standard. Ramp slopes for public and residential buildings.

NBC India Part 3

National Building Code of India. Ramp slope for accessibility and parking gradients.

SANS 10400-S

South African accessibility standard. Ramp slopes and crossfall limits.

Eurocode 1 (EN 1991-1-1)

Actions on structures — roof pitch influences imposed load categories.

People Also Ask

What is a 1:12 slope in percentage and degrees?

1:12 is 8.33% grade and approximately 4.76° angle. It is the maximum running slope allowed for accessible ramps under ADA and IBC.

What is the difference between slope percentage and degrees?

Percent grade is rise ÷ run × 100. Degrees is the angle from horizontal, calculated as arctan(rise ÷ run). They are not the same number. 100% grade is a 45° angle, not 100°.

How do I convert a ratio like 1:20 to a percentage?

Grade (%) = 100 ÷ n. So 1:20 = 100 ÷ 20 = 5%. 1:12 = 100 ÷ 12 = 8.33%. A smaller n means a steeper slope.

What roof pitch is 6:12 in degrees and percentage?

6:12 pitch means 6 units rise per 12 units run. That is 50% grade and approximately 26.57° angle.

What is the minimum slope for drainage pipe?

It depends on pipe diameter. A common rule: 100 mm pipe needs about 1:60 (1.67%), 150 mm pipe about 1:80 (1.25%), and larger pipes can be flatter. Always check the local sewer authority standard.

What is the maximum slope for a wheelchair ramp?

1:12 (8.33%) for ADA and IBC in the United States. Some countries allow 1:10 for short ramps in existing buildings, but 1:12 is the international benchmark. Cross slope is limited to 1:48 (2.08%).

What is the maximum road gradient?

Motorways: 3–4%. Rural roads: 6–8%. Residential streets: 12% (14% for very short sections). Steeper than 12% and heavy vehicles struggle, especially in wet conditions.

How do I measure slope on site without a level?

Use two string lines and a line level, or a laser level. Measure the vertical difference (rise) between two points a known horizontal distance apart (run). Divide rise by run and multiply by 100 for percent grade. A smartphone clinometer app can give a quick angle check, but verify with a physical level for anything critical.

Why is 100% slope equal to 45 degrees?

100% grade means rise equals run. When the rise and run of a right triangle are equal, the angle is 45°. The tangent of 45° is 1, and 1 × 100 = 100%. That is why 100% grade is 45°, not 90° or 100°.

Related Calculators

Verify every slope against the project specification and local code before construction.